Inside/Outside Plant Structured Cabling

http://marylandinternationalschool.org/{{url}} As project manager for the installation of structured cabling within a 220,000 square foot county administrative and correctional facility, The Second Wind Group was responsible for overseeing all aspects of the low voltage contractor’s scope of work for inside and outside plant cabling..

http://vomchildrensfoundation.org/�€Ž The construction site incorporated multiple support buildings and an existing jail which was slated for renovations and upgrades.  Challenges during the phases of construction involved numerous design clarifications and coordination with the prime electrical contractor and the general contractor.

Despite considerable delays due to owner requested changes during construction, and undertaking work outside the original scope of contract, the communications infrastructure was delivered on time as a result of adjusting appropriately for manpower while managing the substantial changes which took place between the owners, architect and general contractor.